Remediation of Concrete Structural Columns & Beams SWMS
Professionally Customised for Your Business
- Professionally customised for your business
- Your Logo and Business Details Included
- Editable Microsoft Word (.docx) format
- Compliant with Australian WHS requirements
- Fast turnaround — typically within 1 business day
- Digital access through JobsiteGo (included with purchase total over $797)
$129.00
GST Included
Secure Checkout
100% Australian Owned
24hr Support
Secure Checkout
100% Australian Owned
24hr Support
Australian Compliant
Prepared in accordance with Safe Work guidelines and relevant Australian Standards.
Product Description
Concrete remediation work requires careful planning to protect the structural integrity of existing buildings while managing the hazards associated with concrete breakout, exposed reinforcement, working at height and reinstatement activities. The Remediation of Concrete Structural Columns & Beams SWMS is intended for demolition contractors, remediation specialists, construction businesses and principal contractors undertaking structural concrete repair works on commercial, industrial and civil construction projects. It helps businesses safely plan, manage and document remediation activities while supporting site-specific risk management and compliance with Australian WHS requirements.
Structural concrete remediation often involves removing deteriorated concrete, exposing reinforcing steel, preparing repair surfaces and reinstating damaged structural elements without compromising surrounding structures. These activities require coordinated planning, engineering oversight where applicable, effective dust control and clearly defined exclusion zones to protect workers and nearby trades.
This SWMS follows the documented work sequence from preparation through to reinstatement and final housekeeping, providing a practical framework that can be reviewed and customised to suit individual projects.
Activities Covered
- Reviewing structural drawings and remediation scope.
- Establishing work zones and exclusion areas.
- Checking and isolating services before work commences.
- Installing temporary structural support where required.
- Controlled breakout and removal of defective concrete.
- Exposing, cleaning and treating reinforcing steel.
- Minor saw cutting where applicable.
- Surface preparation and structural reinstatement.
- Installation of formwork where required.
- Application of repair mortars or concrete.
- Curing, stripping and final site cleanup.
Hazards Addressed
The SWMS addresses hazards that may include:
- Structural instability during remediation works.
- Falling debris and work at height.
- Silica dust exposure.
- Manual handling injuries.
- Exposure to live services.
- Flying particles and power tool hazards.
- Chemical exposure from repair products.
- Mobile plant interaction.
- Slips, trips and housekeeping hazards.
Control Measures Included
Depending on the selected work method and project requirements, the SWMS includes controls such as:
- Reviewing structural drawings and engineer’s remediation scope.
- Installation of exclusion zones and physical barriers.
- Service scanning and isolation prior to breakout.
- Temporary propping where specified by the engineer.
- Controlled concrete breakout using suitable equipment.
- Dust suppression and extraction methods.
- Inspection and protection of reinforcing steel.
- Safe use of cutting equipment and engineered repair methods.
- Safe curing, stripping and waste management procedures.
PPE Requirements
The source document specifies PPE including:
- Hard hat.
- High-visibility clothing.
- Safety footwear.
- Gloves.
- Eye protection.
- Hearing protection.
- Dust mask.
Additional PPE may be required depending on site conditions, access methods and the products used during remediation.
Plant and Equipment
Plant and equipment may include:
- Concrete scanning systems.
- Electric demolition hammers.
- Chipping guns and hand-held jackhammers.
- Concrete or wall saws.
- Angle grinders.
- Needle scalers and wire brushes.
- Temporary propping systems.
- Scaffolding or elevated work platforms.
- Dust suppression equipment.
- HEPA industrial vacuums.
- Manual handling aids.
Hazardous Chemicals
Where applicable, the work may involve:
- Bonding agents and primers.
- Rust converters and corrosion inhibitors.
- Repair mortars and concrete products.
- Curing compounds.
- Concrete release agents.
- Diesel, hydraulic oils and general site chemicals.
Chemical products should always be managed in accordance with Safety Data Sheets and project-specific procedures.
Emergency Planning
The SWMS includes emergency response procedures covering medical emergencies, service strikes, electric shock, fire, explosion and the unexpected discovery of asbestos-containing materials, together with reporting and communication requirements.
What’s Included
This editable Microsoft Word SWMS may include:
- Step-by-step work activities.
- Hazard identification and risk controls.
- PPE requirements.
- Plant and equipment guidance.
- Emergency response procedures.
- Worker responsibilities.
- Legislative references.
- Consultation and worker sign-off records.
Who This SWMS Is For
Suitable for:
- Demolition contractors.
- Structural remediation contractors.
- Construction businesses carrying out concrete repair works.
- Principal contractors coordinating structural remediation projects.
- Workers undertaking the documented remediation activities.
Australian WHS Requirements
The source document references applicable Australian WHS legislation, regulations and Codes of Practice relating to demolition work, falls, hazardous chemicals, plant and workplace risk management. Every SWMS should be reviewed and customised to reflect the specific workplace, engineering requirements, structural conditions and project hazards before work begins.
Why Choose Tradies Compliance?
Tradies Compliance SWMS documents are developed to help construction businesses implement consistent, professional safety documentation across remediation projects. Delivered in an editable Microsoft Word format, they can be efficiently customised to suit individual worksites while supporting safe planning, supervision and documentation of high-risk construction activities.
✔ Editable Microsoft Word (.docx)
✔ Professionally customised
✔ Your company logo
✔ Business detail
✔ Unlimited edits
✔ Lifetime updates
✔ Risk assessment
✔ Safe work procedures
✔ PPE requirements
✔ Emergency procedures
✔ Review section
✔ Signature page
Digital Access through JobsiteGo
Businesses spending over $797 annually receive complimentary access to JobsiteGo, allowing your customised SWMS library to be securely stored, managed and accessed online.
Online access
Mobile friendly
Cloud storage
How long does customisation take?
Usually under 24 hours. Provisions can be made if you need them faster.
Can you add our logo?
Yes! At checkout you will have the opportunity to send us your logo.
Is the SWMS editable?
Yes – your SWMS comes in Word format for easy editing.
Can I order multiple SWMS?
Yes. You can order as many SWMS as you require.
Are there discounts for multiple purchases?
Yes. The more you order, the more discount you receive. Discounts are applied at checkout.
Document Type
Safe Work Method Statement
Customisation
Included
Turnaround
Within 1 Business Day
Digital Access
Through JobsiteGo
100% Australian Owned
Proudly supporting Australian businesses and jobs.
